GERMANY: Deutsche Bahn will close Berlin-Spandau to long-distance and regional trains from 15 October to 11 December 2027. The eight weeks are the final phase of the Hannover–Berlin renovation.
DB set out the final phase on 20 November, together with its service plan from the timetable change on 13 December. For the eight weeks, the whole section between Fallersleben, near Wolfsburg, and Spandau will be closed.
The first full closure of that section, in place since 2 October, ends on 12 December. Regional trains then return to parts of the line, and long-distance trains stay on a diversion that adds about 80 minutes until the works end.
In the final phase, DB InfraGO, the group’s infrastructure manager, bundles several projects at Berlin’s western entry to concentrate the disruption in one period. Track, switches and signalling around Spandau will be renewed, and the electronic interlocking at Wustermark marshalling yard is due to be commissioned.
During the eight weeks, regional lines RE2 and RE8 from Nauen will run via Potsdam and Wannsee, and long-distance trains from Hamburg will be diverted over Berlin’s northern outer ring. RB10 and RB14 are planned to run about every 30 minutes between Nauen and Falkensee. The S-Bahn at Spandau is not affected.
More stops in Stendal, still 80 minutes longer
From 13 December, nine additional IC train pairs a day are due to run every two hours between Magdeburg and Stendal, giving Stendal more IC stops. A better connection in Braunschweig is to cut the trip from Wolfsburg to Berlin from about three hours to about two and a half, and the return trip by about 15 minutes. Before the works it took about an hour, the news agency dpa reported.
Trains between Hannover and Berlin keep running via Braunschweig and Magdeburg. Freight is diverted the same way, and a second freight diversion via Halle and Eichenberg is due from the end of January 2027.
Slab track from the 1990s
By December 2027, DB InfraGO plans to replace or build more than 214 switches and renew about 357 km of track, 100 km of overhead line and 52 km of the slab track laid on the high-speed line in the 1990s.
Hannover–Berlin is one of three corridors scheduled for 2027 in the revised programme of 13 renovations for 2027–2031, which the federal transport ministry and DB InfraGO presented in October. The other two are Rosenheim–Salzburg and Fulda–Hanau.
Elsewhere on the route, the replacement service during the final phase is expected to resemble the first construction phase, from 2 October to 12 December 2026, DB said. It is still being coordinated.